Chamkoria Chalets & Apartments

Construction updates

13th March 2010


The reception floor area has been tiled and the preparatory work has been done for painting the walls and the ceiling. As soon as the weather warms up over the next couple of weeks this room can be painted. As you can see from the photos there is a lovely wooden feature wall in the reception around the stone fireplace with chunky shelves to the right hand side.

Most of the swimming pool area has now been tiled using a beautiful cream stone effect tile with mosaic border and it is starting to look really nice. The ventilation for this swimming pool area was also installed recently.

The glass balcony railings have now been fitted on all apartments. The wooden railings have been installed on the ground floor of the apartment building which really finishes off the front of the building.

We are still somewhat restricted by the weather at the moment which is to be expected but the spring weather should arrive in the next few weeks to enable us to work on all tasks.