Chamkoria Chalets & Apartments
Construction updates
27 June 2009
Over the last few weeks the weather has been very changeable. We have had nice morning sunshine but in the afternoon fierce thunderstorms which make it difficult to work outside.
The work has continued however. The outside of most chalets is now nearing completion and we have started to work on the wood and stone on the outside of the apartment building.
Inside we are continuing with the plastering. 4 of the chalets are now plastered and the others will be finished in the next 10 days. At the same time we are working on the wooden ceilings on the top floor of the chalets.
Inside the apartments we have completed the plastering on levels 1,2 and 3. Next week we will start the plastering on level 4. Work on the second phase of electricity and water connections is ongoing.
The ceramic tiling has also started and we have included some photos of the bathrooms.
8 June 2009
For the last few weeks we have continued with the external wood and stone work and also internally we have been progressing with the plastering. At this stage of the project there are alot of similar tasks going on in each property. As a result some of the photos are very similar.
Several of the chalets now have the stone and wood work completed on the outside. We have also started internal plastering in chalets 5 and 6 and later in the week we will start on another 2 chalets. The internal water systems in the chalets have been pressure tested and in the next few days we will begin the tiling of the bathrooms.
Work is also continuing on the apartment building. The velux roof windows are being installed and the roof finished. Internally the plastering work in going very well. This is one of the biggest tasks at the moment. The apartments on the first and second floor have now been plastered and this week we are working on the third floor apartments.
Please check back again in a couple of weeks for more updates.


