29 July 2009
We have made good progress with the plastering and the majority of properties now have this completed. The final concrete floors are being poured in the apartments at the moment and will be drying out over the next couple of weeks.
The tiling work for the bathrooms continues and all three choices of bathroom tiles can now be seen. The white bathroom suites will be delivered shortly and we will start installing them.
Tiling work has also started on the balconies. Similarly tiling in the kitchens of the chalets has commenced.
All the fireplaces in the chalets are finished and you can see the lovely stonework on the chimney.
12 July 2009
The plasterers have been hard at work and most of the chalets are now complete, along with the first 3 floors of the apartment building. It really is a huge task but they are getting through it and the remaining apartments should be plastered in the next couple of weeks.
All of the wooden ceilings on the top floor of the chalets are finished and the final floors of they are being poured at the moment. Some of these floors have already been poured and will be drying out over the next couple of weeks.
The first fireplace is currently being built and you can see the lovely shape it will be once once finished.
The tiling work on the bathrooms is continuing and below you can see an example of the Classic Crema style bathroom.